WB-57 status report - Tim Miller

GRIP Banner

WB-57 status report - Tim Miller

WB-57

Flight Date: 
Fri, 08/13/2010
Sortie Number: 
N/A

This is both a test of the system (on doing Platform Sci reports) and a short status report for the WB-57 instruments.  HIRAD is still targeting Aug 23 to arrive at Ellington, but the engineering team has given us a heads up that it may not ship from Huntsville until that day.  Meanwhile, we are still working toward the Aug 23 arrival at Ellington.  AMPR will join HIRAD on the WB-57 1-2 weeks later.

 